The Euclid Creek Tunnel brings cleaner water to Cleveland

Project Overview

70 million
gallons of stormwater/wastewater capacity
18,000 feet
in length
3,000 feet
underneath Lake Erie
Our award-winning design on the Euclid Creek Tunnel provided an innovative, cost-effective solution for cleaner water in Cleveland.

Addressing Cleveland's sewer overflow challenges

Built around 1900, the oldest sewers in greater Cleveland carry sewage, stormwater, and industrial waste in a single pipe. More than 60 times a year, after heavy rainfall, sewers in the Euclid Creek area overflow, threatening the quality of waterways.

In 2010, the sewer district reached an agreement with the US and Ohio Environmental Protection Agencies and the US Department of Justice on a new plan to meet the requirements of the Clean Water Act over a period of 25 years.

The Euclid Creek Tunnel was the first of seven combined sewage overflow (CSO) tunnels that will relieve the Cleveland sewer system. (See video.) The tunnel was designed to hold about 70 million gallons (265,000 cubic meters) of combined stormwater and wastewater. After heavy rain, the combined sewage is pumped to the Easterly Wastewater Treatment Plant.

Located 190 to 220 feet (58 to 67 meters) below ground, the tunnel is 18,000 feet (5.5 kilometers) long and 24 feet (7.3 meters) in diameter. About 3,000 feet (914 meters) of the tunnel passes underneath Lake Erie. A tunnel boring machine (TBM) known as Mackenzie bored through shale to create the tunnel.

Innovative tunnel design and construction

Mott MacDonald was the lead consultant responsible for overall project management and administration, TBM specifications, and design of the tunnel lining, ventilation, and other aspects of the project.

We introduced several key innovations:

  • Bolted, gasketed, and precast concrete segments to build the tunnel. The use of concrete segments in rock is rare, and few if any projects had used them in shale.
  • Concrete segments reinforced with steel fiber instead of rebar, another feature that is rare in the US.
  • A rapid-gel two-part grout system, apparently the only one of its kind in the world. To fill the space between the concrete segments and the rock wall, grout was injected through the tail of the TBM.

Our work on the tunnel required successful collaboration between the contractor, machine supplier, grouting specialists, and others.

The use of steel-fiber-reinforced concrete segments cut four months from the construction schedule and saved the sewer district considerable costs. Our design enabled one-pass construction of the tunnel, reducing risks due to overbreaks and mine stoppages, decreasing infiltration, and increasing quality and safety. The contractor was able to bore the tunnel at rates of up to 110 to 130 feet (33 to 40 meters) per day.  

Safeguarding Cleveland's waterways

Completed in 2013, the Euclid Creek Tunnel now prevents millions of gallons of overflow sewage from reaching Euclid Creek and Lake Erie, helping safeguard public health and the environment in the greater Cleveland area.

In 2021, the Easterly CSO Tunnel System (including the Euclid Creek Tunnel, Dugway Storage Tunnel, and Easterly Tunnel Dewatering Pump Station) received the Grand Award from the Ohio chapter of the American Council of Engineering Companies (ACEC).